Great progress at Belle Vue, Holbeach

Posted on 21st October 2014

Station House
The replacement windows are in manufacture and were due end of October. Manufactured by local firm Nene Joinery. All ground floor slabs are now concreted. New stairs to first floor are now fitted.



Lower roof due to be tiled w/c 20th October. Once in and dry, we will screed the ground floor flats.

Roads and Sewers.
Site road due to be tarmacked 20th

 

Services
Water main has been laid around the site road, with Gas main and electric duct following on. Telephone pole has been relocated and new BT boxes constructed to Station Road.

Plots 1-14
These are on program. Plots 13 and 14 roof trusses due next week, with a view of standing the roof the following week. 


Piling for plots 15-22 start wc 20th October.

Everything is on schedule for delivery of the first properties in late March 2015.